1. Investors study conditions and the actual subleasing of industrial zones with IDICO.
2. Investors agree conditions for signing Land Subleasing Memorandum (MOU) with IDICO:
- Validity of MOU is 04 months;
- Making the deposit payment equivalent to 5% amout of infrastructure using fee, this deposit shall be deducted from the payments of Land Subleasing Contract;
- Within 04 months, the investors must implementing the procedure of the Investment Registration Certificate and Establishing a new Enterprise of project to sign the Land Subleasing Contract with IDICO;
3. The procedures which investors shall implement:
3.1. Implementing the procedure of applying for principle approval on Investment project with the Authority (It would take from 15 to 30 days);
3.2. If the investment project is approved, the investors continue to carry out the procedure for the Investment Registration Certificate (IRC) (I would take 15 days).
3.3. At the same time, the procedure for preparing and applying for the approval of the Environmental Impact Assessment (EIA) are submitted at the EIA authority (It would take 60 - 90 days)
3.4. After getting the Investment Registration Certificate, Investor apply for the Enterprise Registration Certificate (ERC) for project.
3.5. Within 30 days, from the date issuance of the IRC and ERC, the Land Subleasing Contract will be signed by the 2 parties;
3.6. Applying for a construction permit:
- After the investors sign the Land Subleasing Contract; At the same time, the Project was approved the EIA; The design has been approved for fire prevention and fighting, the investors carry out the procedures for applying for a construction permit with the Authority.
- After being granted the construction permit, investors will carry out the construction of the Project.